I have to pull everyone off start-ups for Wednesday so we can finish up a project on an apartment building that was scheduled well over a month ago where we need to connect with 40 tenants at the same time. We hope to finish the job within 4-5 hours, but after that Jesse has a sprinkler main in Eagle to dig up where there is a huge water leak. This afternoon I will be working on more backflow tests and Package “C” customers.
Thursday I will be putting Jesse in Nampa and Caldwell after the valve he digs up on Wednesday is repaired, and Justin in Kuna and Meridian to take care of any Package “A” and “B” remaining. Yesterday Justin took care of all the Package “A” customers we had as of yesterday morning in Eagle, Star, Meridian, and Boise. Thursday I will put Justin on any Package “A”
I will continue with backflow tests and Package “C” customers on Thursday and Friday.
Justin ran into a few locked gates yesterday so couldn’t get the sprinkler system turned on. Gates need to be unlocked for us to do our job. It is very frustrating with all the chaos we have during start-ups and blowouts to drive to a property and not be able to work. It really eats up a lot of time out of our day.
If anything changes on today’s schedule, I will update this post.